Wednesday, 28 March 2018


PLUMBING INSTALLATION ( SANITARY SYSTEM )

                     Water supply is the process for 'water in', while plumbing installation is the process for ' water out '. Each process has their own system such as water supply in low rise building use direct and indirect system, meanwhile water supply in high rise building use booster system. So, for plumbing system ( sanitary system ) use sewer system. The progress of the sewer system is shown below:

SEWER

Pipe for carrying the sewage and liquid waste 

SEWERAGE
Collect, treat and dispose
SEWERAGE
The thing that pass on chemical

SEWAGE DISPOSAL SYSTEM
Disposing of sewage by septic tank or mechanical treatment



There are 2 ways of plumbing installation:


Drainage Above Ground
                                                                              
Source: Google Images

  Drainage Below Ground



Source: Google Images
Sanitary Fittings:

Cistern (Disc Type)
Source: Google Images







Water Closet

Source: Google Images

Urinal Bowl
Source: Google Images

Trap(to hold foul air)

Source: Google Images

Pipe Gradients

All above ground and below ground horizontal drainage pipes should be laid to an adequate gradient. Gradients from 1 in 40 to 1 in 110 will normally give adequate flow velocities. A gradient of 1 in 80 is suitable for commencing calculations for pipe schemes.

If the gradient is not steep enough, i.e. less than 1 in 110, then the pipe could block if the solids slow down and become stranded. The fall in a pipe may be defined as the vertical amount by which the pipe drops over a distance. The distance can be between sections of pipe or between manholes. The diagram below show pipe fall and distance.
GRADIENT = FALL / DISTANCE

For example is a 36 metre section of drainage pipe has a fall of 0.4 metres, calculate the gradient.
Gradient = 0.4 / 36
Gradient = 0.0111

This can be converted into a gradient written as a ratio or 1: some number.
Gradient = 1 / 0.0111 = 90

Gradient = 1 in 90



CASE STUDY
B12,FAKULTI ALAM BINA
SANITARY SYSTEM

Gate Valve













                                                                                                                             Pillar Tap and Sink








Trap










               Cistern and Water Closet









Toilet Floor Plan in B12



Level 3 Block D

Level 4 Block B

Level 5 Block B

Level 2 Block B

Level 5 Block D



B 12 use TWO PIPE SYSTEM installation